Can you ask a court to reduce excessive liquidated damages in China? The 30% rule, who must prove it, and "no adjustment" clauses

Yes. Article 585 of the Civil Code (民法典) provides that where the agreed liquidated damages are excessively higher than the loss caused, the court or arbitration institution may reduce them appropriately at a party's request; the judicial interpretation provides that damages exceeding the loss by 30% can generally be found to be excessively higher than the loss. The party asking for a reduction bears the burden of proof, a deliberate breach is generally not reduced, and a clause stating "no adjustment" does not prevent a request for adjustment.

You can ask for a reduction, but you must raise the request yourself and produce evidence. Article 585 of the Civil Code of the People's Republic of China (民法典) provides: where the agreed liquidated damages are lower than the loss caused, the people's court or arbitration institution may, at a party's request, increase them; where the agreed liquidated damages are excessively higher than the loss caused, the people's court or arbitration institution may, at a party's request, reduce them appropriately. Article 65 of the Supreme People's Court's Interpretation on the Application of the Civil Code of the People's Republic of China (Contract Part, General Provisions) (《关于适用〈中华人民共和国民法典〉合同编通则若干问题的解释》) (Fashi [2023] No. 13, 法释〔2023〕13号) further provides that where the agreed liquidated damages exceed the loss caused by 30 percent, the people's court can generally find them to be excessively higher than the loss caused.

How the court decides whether liquidated damages are too high

Article 65 of the Interpretation requires the court to measure against the loss defined in Article 584 of the Civil Code. Article 584 provides that the amount of damages shall be equivalent to the loss caused by the breach, including the benefits that could have been obtained had the contract been performed, but shall not exceed the loss that the breaching party foresaw or should have foreseen, when concluding the contract, might be caused by the breach.

On that basis the court also takes into account the parties to the contract, the type of transaction, how the contract was performed, the parties' degree of fault, the background to performance and other factors, and decides in accordance with the principles of fairness and good faith. "Exceeds the loss by 30%" is a general standard, not a mechanical formula: where it is exceeded by more than 30%, the damages can generally be found too high, but how far they are finally reduced is decided by the court taking all the factors into account.

Who must prove it

Article 64 of the Interpretation provides:

  • where the breaching party claims that the agreed liquidated damages are excessively higher than the loss caused by the breach and asks for an appropriate reduction, it bears the burden of proof;
  • where the non-breaching party claims that the agreed liquidated damages are reasonable, it must also provide corresponding evidence.

So the party that wants the damages lowered must show roughly what the other side's actual loss is, for example that the other side quickly found a replacement transaction, or that the loss is small. If the other side thinks the damages are reasonable, it must also produce evidence of its loss.

Does a clause saying "liquidated damages shall not be adjusted" work

No. Article 64, third paragraph, of the Interpretation provides that where a party relies only on a contract clause that the liquidated damages are not to be adjusted as the ground for asking that they not be adjusted, the people's court does not support the claim. That is, even if the contract says "both parties waive the right to ask for adjustment of the liquidated damages", you can still ask the court to adjust them.

When and how to raise it

  • It can be raised by counterclaim or by defence: Article 64, first paragraph, provides that where a party asks for liquidated damages to be adjusted by way of a counterclaim or a defence, the people's court shall support this in accordance with the law. If you are sued for payment of liquidated damages, it is enough to raise it in your defence.
  • Also plan an alternative claim when you deny the breach: Article 66 provides that where a defendant defends on grounds such as that the contract was not formed or that there was no breach and has not asked for the liquidated damages to be adjusted, the court shall explain to it whether, if the defence fails, it asks for the liquidated damages to be adjusted. The safe approach is, while arguing there was no breach, to also state that "even if there was a breach, the liquidated damages are too high and an adjustment is requested".
  • Where a party did not appear at first instance: where a defendant did not appear in the first instance for objective reasons, but appears in the second instance and asks for the liquidated damages to be reduced, the second-instance court may, after full presentation of evidence, cross-examination and argument, decide in accordance with the law to reduce them appropriately.

When it is hard to get a reduction

  • Deliberate breach: Article 65, third paragraph, provides that where a party in deliberate breach asks for the liquidated damages to be reduced, the people's court generally does not support the request.
  • Liquidated damages for delay in performance: Article 585, third paragraph, of the Civil Code provides that where the parties have agreed liquidated damages for delay in performance, the breaching party must still perform its obligation after paying them. Paying liquidated damages does not release it from continuing to perform.
  • The other side's loss is really large: if the other side can prove that its actual loss is close to or exceeds the liquidated damages, the court will not lower them; where the agreed liquidated damages are lower than the loss, the other side may also ask for them to be increased.

An example

A renovation company signs a contract with a homeowner providing for liquidated damages of 1% of the total contract price for each day of delay in completion; the total contract price is CNY 200000. The works are delayed by 30 days and the owner claims liquidated damages of CNY 60000. In the proceedings the renovation company defends and submits evidence that the rent for other housing and other expenses of the owner during the delay came to about CNY 10000 in total. Under the judicial interpretation, liquidated damages that exceed the loss by 30% (that is, about CNY 13000) can generally be found excessively higher than the loss, and the court will take into account the reasons for the delay, the parties' fault and other factors and reduce the damages at its discretion. If the renovation company stopped work on purpose in order to take on a more profitable job, that is a deliberate breach, and a request for reduction would generally not be supported.

What to do in practice

  • Collect evidence that the other side's actual loss is small, such as that it has found a replacement transaction or how market prices have changed.
  • State clearly in the statement of defence or the counterclaim: "the liquidated damages are requested to be reduced appropriately in accordance with the law".
  • Note Article 591 of the Civil Code: where the other party has not taken appropriate measures to prevent the loss from growing, it may not claim compensation for the part of the loss that has grown, which also affects how the loss is determined.

When you need a lawyer

Where the liquidated damages are large, the contract terms are complex (for example, liquidated damages, a dingjin (定金) and damages clauses are all agreed), or the other side has already applied for arbitration or sued, it is advisable to consult a lawyer licensed in China early, to prepare evidence of the actual loss and to decide whether to raise the request for adjustment by way of defence or counterclaim.

Step by step

  1. Check the liquidated damages clause in the contract — Confirm how the liquidated damages are calculated, whether they are for delay in performance, and whether a dingjin (定金) or compensation for loss was also agreed.
  2. Estimate the other side's actual loss — On the basis of Article 584 of the Civil Code, estimate the loss and the expected benefits the other side lost through the breach, and compare whether the liquidated damages exceed the loss by 30%.
  3. Collect evidence — Collect evidence that the other side found a replacement transaction, that its loss is small, that it was itself at fault, or that it did not take steps to prevent the loss from growing.
  4. Make the request in litigation or arbitration — Ask the court or arbitration institution, by defence or counterclaim, to reduce the liquidated damages appropriately; if you deny a breach, also make an alternative request for adjustment.

Documents you need

  • The original contract and any supplementary agreements
  • Evidence of performance and of the facts of the breach
  • Evidence of the other side's actual loss (replacement transactions, market prices and so on)
  • Correspondence between the parties and records of demands for performance
  • A copy of the statement of claim or the application for arbitration

Common mistakes to avoid

  • Thinking the court will lower the liquidated damages on its own and not making the request yourself
  • Only arguing that you did not breach and not making an alternative request for adjustment
  • Thinking that because the contract says no adjustment, adjustment is impossible
  • Asking for a reduction without any evidence that the other side's actual loss is small
  • Thinking that having paid liquidated damages for delay means you no longer have to perform

Frequently asked questions

By how much do liquidated damages have to exceed the loss to be too high?

Article 65 of the Supreme People's Court's Interpretation on the general provisions of the Contract Part provides that where the agreed liquidated damages exceed the loss caused by 30 percent, the people's court can generally find them excessively higher than the loss caused, but the final decision still takes into account how the contract was performed, the degree of fault and other factors.

If the contract says the liquidated damages may not be adjusted, can I still ask for a reduction?

Yes. Article 64 of the judicial interpretation provides that where a party relies only on a contract clause that the liquidated damages are not to be adjusted as the ground for asking that they not be adjusted, the people's court does not support the claim.

Will the court lower the liquidated damages for me on its own initiative?

The Civil Code provides for a reduction at a party's request, so you need to ask. But if you only argue that there was no breach and do not ask for an adjustment, the court shall explain to you whether you ask for the liquidated damages to be adjusted.

If the liquidated damages are too low, can I ask for them to be increased?

Yes. Article 585 of the Civil Code provides that where the agreed liquidated damages are lower than the loss caused, the people's court or arbitration institution may increase them at a party's request, but you need to provide evidence of the actual loss.