Building Contract for House Renovation or Construction — Indonesia

Renovating or building a house in Indonesia and want a written agreement with your contractor that you can understand in English? This free wizard creates a perjanjian pemborongan (building contract) under the Indonesian Civil Code (KUHPerdata). You answer the questions in English and get the contract in Indonesian and English, paragraph by paragraph.

The contract covers the scope of work with drawings and cost estimate (RAB), who provides the materials, permits, a fixed contract price, staged payments after joint inspection, retention, the schedule and delay penalty, workers and safety, handover and maintenance period, the contractor's 10-year liability, termination and consumer rights. The Indonesian text is the legally binding one.

For renovating or building a residential house by an individual contractor or a small business. Not suitable for government projects, large multi-storey or commercial buildings subject to construction services rules and business certification, work requiring a separate designer and supervisor, or where the contractor provides financing. Seek advice from an advocate or a construction expert for high-value projects.

What the contract covers

  1. Scope of work
  2. Building materials
  3. Permits
  4. Contract price
  5. Payment
  6. Schedule
  7. Workers and safety
  8. Handover and maintenance period
  9. Liability for the building
  10. Termination of the agreement
  11. Consumer rights
  12. Dispute resolution
  13. Closing

How it works

  1. Answer the questions step by step.
  2. Check everything on the review page.
  3. Download the contract or send it for e-signing.

Frequently asked questions

Can a contractor in Indonesia raise the agreed price?

Not on the grounds of higher wages, material prices or changes to the work, unless the changes and their price have been approved in writing by the owner (Article 1610 KUHPerdata). Approve every change in writing.

How long is a contractor liable for a house in Indonesia?

If a building contracted for a fixed price is destroyed in whole or in part because of a construction defect or unsuitable ground, the contractor is liable for ten years (Article 1609 KUHPerdata).

Can I end a building contract after the work has started?

Yes. Under Article 1611 KUHPerdata the owner may terminate the agreement even after the work has started, but must fully compensate the contractor for costs incurred and loss of profit.

Why should I inspect each stage before paying?

Under Article 1608 KUHPerdata, payment for a stage is deemed approval of the part paid for. This contract therefore provides that the owner and contractor jointly inspect each completed part before payment.

Is the text I type myself translated?

No. Text you type yourself, such as the scope of work or the payment stages, is copied into both language versions exactly as written. If you want it understood in both languages, write it in Indonesian and English.

Official sources